Cross Passage Blackwall, London
Conisbee were appointed by Browne Developer Services to design, obtain approval, and build a temporary above-ground drainage system to service the deep-bored dewatering pump wells that serviced the Tunnel Boring Machines (TBMs) used as part of the Blackwall tunnel project.
The dewatering wells designed and installed by WJGL were set at a depth of 90 m into the underlying chalk strata and had a continual pump rate of 380 l/s.
As part of the process, Conisbee designed a twin wall pipe system measuring 355 mm in diameter with HDPE and fusion-welded joints which were laid at ground level along a disused footpath. A series of ground anchors and trust blocks were designed to ensure minimal embedment into the ground due to the presence of existing buried service ducts.
The well points were connected into the pipe arrangements at determined sections, with pressure valves incorporated into the design. The pipe system was carefully orientated to a discharge point on the River Thames, whereby Conisbee designed a bespoke hydraulic diffuser unit system to discharge the pumped flow into six outlet pipes in order to reduce the flow rate and avoid erosion of the River Bed.
The design was approved by the Environment Agency and Port of London Authority within eight weeks and was installed and operational for 18 months.
Client:
Dragados Sisk Joint Venture for Cross Rail
Architect:
N/A
Project Value:
£500,000