The site comprises a long strip of land between Somerleyton Road and the railway embankment development and comprises six separate development blocks.
There are five new buildings along with a refurbished masonry block to incorporate 304 new homes, a community theatre, a community centre and nursery, creative / cultural office space, educational space, a chef’s school and public realm redevelopment including a street gym.
Conisbee were appointed for Civil and Structural Engineering Design services for the entire development including the renovation of the locally listed Carlton Mansions. We have developed the structural designs for all six buildings as well as the below ground foul and surface water site-wide below ground drainage.
The project has some challenging site constraints, including LUL Victoria line tunnels running below the footprint of the site. We liaised directly with LUL to obtain record information and organise additional survey information to determine the make-up, location and condition of the existing tunnels so that this information could be incorporated into our design for the buildings positioned over the tunnels. Developing different foundation solutions for the development at feasibility stage was key in determining the most viable approach for the overall massing of the scheme by ensuring that predicted movements of the below ground tunnels remained within tolerable limits.
Additionally, there is an existing Network Rail embankment adjacent to the boundary of the site over the full 450m length of the site. In many locations our proposed new foundations encroach on the support zone for the embankment so we have liaised with Network Rail to develop solutions and construction sequences which will not undermine the stability of the embankment and the railway lines above.
Each block has a structural system appropriate for the building type and layout, with rc frame being mainly used on the residential blocks and steel frame for the theatre. Alterations to the retained building were carried out in masonry and steel, with structural repairs and strengthening also required to the dilapidated structure. The existing foundations for the building were re-used to minimise embodied carbon on the scheme.
With respect to the civil engineering aspect of the project the drainage design has incorporated sustainable drainage systems to reduce surface water run-off from the site and provide treatment of surface water before discharge to the ground and the public sewer system. These systems include green roofs, permeable paving and surface water infiltration beds.
Innovation was required in the foundation solutions which were developed for the building structures located over the underground tunnels. A variety of methods have been adopted including 15m span reinforced concrete foundation beams supported by 1050mm diameter bored piles either side of the tunnel exclusion zones, ground bearing raft foundations where piling and bridging solutions were not feasible due to the positioning of the below ground tunnels and underpinning of existing foundations to allow for increased loading due to change in use from residential to office space. While the above techniques in themselves are not new methods of construction, incorporating and coordinating the various solutions into the overall design has resulted in quite bespoke and innovative sub-structure design.
hello index Silchester Estate, Londonhello index Pablo Fanque House, Norwich
Conisbee provided Structural and Civil Engineering services for this purpose-built hall of residence for the University of East Anglia for Alumno Developments.
Working with architects Carson & Partners Conisbee designed the 244 unit, 12-storey building as a hybrid structure in both insitu and precast reinforced concrete. The design and construction up to roof level of the frame was carried out in an extremely challenging 10 month programme.
The project needed a rigorous approach to researching the history and surrounding construction to understand the constraints and risks in the ground. Historic basements, solution features in the chalk, an adjacent important 5m retaining site boundary wall and a (vibration sensitive) Gas Governor building supplying Aviva all had to be addressed in developing the design.
hello index Wayland House, Stockwell hello index Ocean Estate, London hello index Morello Towers, Croydon hello index Magna Housing, Cambridge