Menu
hello index Hertfordshire Police Constabulary HQ hello index Oak Hill Crematorium, Hatfield

This award winning project comprises a new single storey Crematorium with integral Machinery Store to the south western corner of the existing Lawn Cemetery, operated by the Welwyn Hatfield Borough Council.

This is accompanied by new associated car park and supplementary roadside parking within the cemetery curtilage. Some road network alterations and extensive landscaping forms part of the scheme, including the addition of two surface water attenuation ponds.

The project also includes  the demolition and clearance of the current chapel and the adjacent redundant Manager’s Lodge complex, with the porte-cochere between and the central colonnade in the cemetery.
A steel frame with a profiled metal deck roof; timber and glulam frame. Façade is mainly brickwork cladding.

The  crematorium is a predominantly braced steel frame with a profiled metal deck roof. To form the chapel, a series of exposed glulam frames were introduced to create an architectural feature and to support the upper timber roof.

To achieve the double height along the chapel, a timber stud wall was built between the lower profiled metal deck roof and the upper timber roof. The timber stud wall will be supported off the steel frame at its base. To form the balcony area inside the chapel, a timber joist floor was used and the timber joist floor is supported by steel cantilevering beams.

SCORS Carbon Calculator

Class C

 

Photography @Peter Bennet

hello index The Nourish Hub, Shepherd’s Bush

Conisbee were appointed to assist with the refurbishment of a vacant post office into an educational space, for the purpose of teaching visitors about healthy cooking and nutrition.

The vision for the Nourish Hub was to provide a democratic social space, welcoming to all. The refurbishment sought to bring disused space to the back of Edwards Wood Estate back to life by providing an open facility for the local community to engage, learn about healthy cooking, and be served food on a ‘pay as you feel’ basis.

We provided the structural design input for a series of alterations to the existing structure such as openings in existing walls, demolition of walls, providing fixings for the new curtain glazing system and some of the kitchen equipment.

The Nourish Hub won the MacEwen award 2022, an award specifically celebrating architecture for the common good of the people.

 

 

hello index Yaa Centre, London

The Yaa Centre is a community arts project providing facilities for dance/drama and music rehearsals as well as costume manufacture for the Notting Hill Carnival.

The existing site consisted of several buildings that had been linked together and converted into an arts centre. The project saw the demolition of all but one of the existing structures and the construction of a new two-storey steel-framed structure. At ground floor level, there is a large multi-functional space with a sprung floor together with classrooms. At the first floor, a large gallery frames the performance space below. Workshops and offices are provided off the gallery. Within the retained building, a new rehearsal space has been formed which is acoustically separated from the main structure.

Integral to the world-famous Notting Hill Carnival, the Yaa Centre is a community arts project providing facilities for dance/drama, music rehearsals and costume manufacture. To create a new home for the project, this scheme included demolition of a range of old courtyard buildings, retention of one structure and construction of a new two-storey, steel-framed centre. At ground level there is a reception, classrooms and a large, multifunctional space with a sprung floor. At the first floor, a gallery frames the performance space below. Workshops and offices are provided off the gallery. The retained building contains a new rehearsal space which is acoustically separated from the main structure.

 

Photography @James Morris

hello index The Eltham Centre, London

Conisbee were appointed to provide the structural engineering solution for this major flagship leisure development in South East London. This predominantly new build project provides integrated council leisure facilities which included the integration of a Grade II listed library and a ‘one stop shop’ for council services. The scheme includes 3 swimming pools, a healthy living centre, fitness suite, dance studios, an extensive library facility, council offices and facilities for Greenwich Community College

This new-build flagship development provides integrated leisure facilities, a library and a one-stop-shop for council services and included the integration of a Grade II listed library. The scheme includes three swimming pools, a healthy-living centre, fitness suite, dance studios, an extensive library facility, council offices and facilities for Greenwich Community College. We provided the structural and civil engineering solution for this development in south-east London.

The Eltham Centre was constructed using steel and reinforced concrete. Clear-span roofs, not supporting plant, comprise lightweight cladding materials supported on universal beams. Beams over the main swimming pool span onto a main transfer truss. The remainder of the superstructure is in-situ concrete floors supported either on profiled steel decking or solid precast concrete planks. The beams and columns supporting the floors are structural steel transferring the loads to the foundations.

The building achieved a BREEAM Very Good rating.

 

Photography @David Barne

hello index Soap Box, Old Street, London

Soap Box is typical example of a mid 20th century mid-rise development. The existing building comprises four storeys plus a basement, all of reinforced concrete construction. The works involved the refurbishment of ground and basement levels only, with the above three storeys of office space remaining in operation throughout the entire works.

The concrete frame is typical of a commercial property, comprising one way spanning slabs on downstand beams. The scope of our works principally involved alterations to the structure to accommodate new stairs and lifts, strengthening of the pot and beam floors to accommodate dance studios, and amendments to the envelope to create a more modern and exciting look to the building.

The project presented a number of challenges: strengthening the floor above a live substation; achieving the minimum headroom at basement level given the new steelwork and mass of new services; connecting the new drainage infrastructure; and generally having to prove an existing structure that had undergone alterations in the past. Consideration also had to be given to minimising noise disturbance to the above live offices.

 

Photography @Charles Hosea

 

hello index MyPlace Cedars Youth and Community Centre, Watford

Conisbee provided full structural and civil engineering services for this new 2 storey building that replaces a long established youth centre providing enhanced facilities for all sectors of the local community. New facilities include a sports hall, gym, café, ICT and learning resource suite and an all weather sports pitch. The design includes brown and green roofs to help soften the building’s form in order to integrate it with the adjacent park whilst also encouraging biodiversity on the site.

This new two-storey building replaces a long-established youth centre providing enhanced facilities for all sectors of the local community. New facilities include a sports hall, gym, café, ICT and learning resource suite and an all-weather sports pitch. The design includes brown and green roofs to help soften the building’s form and integrate it with the adjacent park while also encouraging biodiversity on the site.

 

Photography @Hufton+Crow

hello index Dellow Day Centre, London

Featherstone Young and Conisbee were appointed by local charity Providence Row to design a new build as part of their day centre facility.

Providence Row provides support and hope to homeless people in Tower Hamlets and the City of London, and the Dellow Day Centre provides essential services such as food, clothing and showers – which help to restore health and dignity to those in difficult circumstances.

The new building is constructed on a tight infill site and replaces an existing outpost building with a new extension block with an increased footprint containing a laundry, clothes store, archive, storage, activity space and art room facilities.

The new structure was originally conceived as a lightweight braced steel frame with piled raft foundations. Due to the long and complex history and previous buildings on the site, the site investigation threw up a number of challenges including the discovery of the foundations of a 20m high chimney from a previous brickworks on the site. As a result of finding a multitude of obstructions in the ground during the SI, the design was changed to deep strip foundations which could accommodate any unexpected obstructions easier than the original piled solution. Conisbee worked closely with the main contractor to ensure that these were installed safely due to the depth of excavation required to get through the made ground and into the load-bearing gravels.

The steel frame was chosen as the best material to meet the tight programme on site as well as satisfying the architectural aspirations for the superstructure to be a light and flexible space with large rooflights and glazing elements. The floors are lightweight timber I joists with a ply deck which keeps the overall weight of the building to a minimum while providing a stiff diaphragm and floor for the office and general purpose spaces in the building.

hello index Dale Youth Boxing Academy & Community Centre, London

Dale Youth Boxing Academy is a community project that Conisbee were proud to be involved with. Following the tragic events in June 2017, a volunteer design team was formed to help with the design and construction of a new boxing gym and community hub under the Westway in Kensington with the help of DIY SOS and the BBC. Featherstone & Young were the architects behind the new gym with Hoare Lee and Galliard Homes committing their expertise and services. B and W Engineers provided the steel frame fabrication for the project working with Modebest for the foundations and ground work.

The scheme includes a 2-storey community building and 1-storey boxing club with mezzanine. This exceptional project received full planning at the beginning of March 2018, under the proviso that the community affected by the tragedy remain involved throughout. The project was completed in September 2018 and opened to the public with two part special on the BBC’s DIY SOS Big Build.

The project was awarded with a RICS 2019 Community Project Award and was runner up in the RICS 2019 Grand Final.